5G Connect Danube Delta - Deliverables

9 apr. 2025
Deliverables Table
Deliverable No Deliverable Name Work Package No Lead Beneficiary Type Dissemination Level Due Date (month)
D1.1 Data Management Plan 1 ORO R PU M18
D1.2 Progress Report 1 1 ORO R SEN M12
D1.3 Progress Report 2 1 ORO R SEN M24
D2.1 Feasibility and impact study on the 5G-CDD envisioned applications 2 OROF R PU M6
D2.2 Demand and requirements for the 5G-CDD envisioned applications 2 ORO R PU M12
D3.1 5G-CDD network architecture definition and design report 3 UNSTPB R SEN M12
D3.2 5G-CDD network deployment and integration activities report 3 ORO R SEN M27
D4.1 5G-CDD applications integration report 4 ORO R PU M27
D4.2 5G-CDD applications acceptance and beneficiaries handover report 4 VBoard R PU M30
D5.1 5G-CDD exploitation and sustainability report 5 UNSTPB R PU M36
D5.2 5G-CDD dissemination and communication activities report 5 UNSTPB R PU M36

The 5G Connect Danube Delta project is funded through the Connecting Europe Facility program of the European Commission, under the framework of 5G and Edge Cloud for Smart Communities, Grant Agreement 101181137.
icon-monitoring